Here’s where we are in construction at Junsay Oaks:

  • Construction is at 50% complete
  • Chair lift started
  • Roofing on Building B (southwest wing) will be complete in 3 weeks
  • All framing will be complete in one week
  • Fire inspections will commence soon

We anticipate completing Junsay Oaks Senior Apartments in the Fall of 2019. For more information about Junsay Oaks and other CHISPA developments, visit our website at www.chispahousing.org.

The following two tabs change content below.

Charla Claessen

Latest posts by Charla Claessen (see all)

Subscribe To Our Newsletter

Subscribe To Our Newsletter

Join our mailing list to receive the latest news and updates from our team.

You have Successfully Subscribed!

Pin It on Pinterest

Share This